Schedule

Week Starting Milestone Deliverables
Feb 3

Sign up for project

  • Names of group members
  • Prioritized list of up to three projects that interest you
Feb 17
or
Feb 24

Kickoff ("release planning") meeting

  • Meeting with customer, instructor, and project manager during which you will discuss high-level objectives and identify requirements for the project
Feb 24
or
Mar 3

Requirements review meeting

  • Meeting with customer and project manager, during which you will clarify any requirements
Mar 17

First iteration planning meeting

  • Meeting with customer and project manager, during which you will identify a set of user stories to complete in first iteration
  • Development environment and source control set up
Mar 24

First iteration update meeting #1

  • Meeting with project manager
Mar 31

First iteration update meeting #2

  • Meeting with project manager
Apr 7

First iteration demo

Second iteration planning meeting

  • Implementation of functionality (and corresponding test cases!) from first iteration user stories
  • First iteration report, including revision of incomplete user stories
  • Meeting with customer and project manager, during which you will identify a set of user stories to complete in second iteration
Apr 14

Second iteration update meeting #1

  • Meeting with project manager
Apr 21

Second iteration update meeting #2

  • Meeting with project manager
Apr 28
or
May 5

Final demo

  • Implementation of functionality (and corresponding test cases!) from second iteration user stories
  • Final report
  • Customer handoff document
  • Meeting with customer, instructor, and project manager